Montage

Individual tombstone
1. Foundations
The individual tombstone assembled is on two prefabricated foundations of reinforced concrete embedded directly on the grave. One in the head second in legs of the mound heaped up on the grave.
2. Levelling
Foundations one ought crosswise to level, instead the foundation in the bed-head we place 2-3cm from bottom foundation and like this we obtain the slope windfall of the water from the tombstone.
3. Subframe
On correctly embedded in the ground foundations we put the bottom of the tombstone(the subframe) which is earlier prepared en bloc to the independent montage.
4.Frame
The frame we arrange on the subframe adverting on the maintenance of equal distances in relation to the subframe.
5. Plate
On the frame we arrange lid plate and we seat her evenly in relation to the frame. On plate we arrange the plinth, then using assembly-openings we join with the cement the plinth and the sepulchral plate.
6. Finishing
After assembling of elements of the tombstone into the whole one ought the tombstone to clean up on dry, and with the then special assembly-glue to fill places of points of junction of elements of the monument..

 

           
       
       
       
       
       
       
       
       
       
       
             
             
             
             
             
             
             
             
           